Developer Requested Improvement Projects

The Wilds 20th Addition

  • Completed work: All underground utilities completed
  • Upcoming work: Paving roads

The Wilds 21st Addition

  • Completed work: Engineering seeking approval to create engineers report at Monday, April 19, City Commission meeting.
  • Upcoming work: Engineering to present engineers report to City Commission for approval to prepare plans and specifications 

Westview Third Addition (Phase 2)

  • Completed work: Construction starting Monday, April 26, 2021.
  • Upcoming work: Install underground utilities.

Westview 4th Addition

  • Completed work: All underground utilities completed
  • Upcoming work: Paving roads

Ninth Avenue NE Sanitary Sewer, Water Mains, Fire and Street Improvements

  • Completed work: Staff to conduct final walkthrough.
  • Upcoming work: Close out projects.